Is there a way for a master sheet to be automatically populated by project sheets? What I mean by this is that I have them linked currently but if I were to add a row to the project sheet would it add the new row into the master sheet?
I am pretty sure that there isn't. I was looking for this a couple months back.
Hi Meg,
You can copy or move new rows automatically with a service like Zapier.
Would that work for you?
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
Hi Meg, agree with the others, not out of the box. We have automated this in the past using a custom app built with the Smartsheet API and Control Center can help out too but I expect you are looking for something less heavyweight!
Helloe Everyone! I’m trying to reference another sheet in Smartsheet, but I’ve noticed that sometimes it loads quickly, while other times it takes a very long time to display the list. Does anyone know why this happens? Is there a way to reduce how often this issue occurs? Today, I can’t get anything to load at all. 😑
Hello - Is there a work around in a Report to list multiple sheets in an order that I choose? Sorting doesn't give me the order in which I want them to appear in the report or in a widget on a dashboard. I would like them in a specific order. Thank you.
I need to revise/expand a filter - the list of items in the filter NOT the filter name - in a dashboard I created. Is this done through the dashboard or through the main data sheet?