Is there a way how the charts in a dashboard can be updated automatically as one add new rows to a database?
Thank you.
Hi yes all the charts update dynamically from the data they are charting so if you are counting rows in a sheet with your graph then when you add more rows they will update (you have to do a manual refresh on the dashboard or set it to auto-refresh every few minutes).
Mick
I don't think that answers the question.
If I have a column with numbers
234527111154
and add a new row,
76
the chart was setup for 5 rows and now should be 6.
This might be possible with Reports, but with the recent delays in Reporting, I can not test to be sure.
Craig
It (my interpretation of the OP's question) is possible with Reports.
Thanks for asking, this led me to a solution I had missed before.
Hi, the bit I missed was using CountIFs to capture all row data then chart from that. That way all row data gets used by the Charts.
Hello, I have two sheets. One is "Current tasks" and one is "Completed tasks". I have the rows (individual tasks) auto number when entered (2026-001, 2026-002, etc.). When the row is marked complete, it is moved to the "Completed task" sheet. The problem I am having is that when the row is moved the other tasks that remain…
Hi, I'm trying to print PDF of my Dashboard but no matter how many times I try, the chart's legend area does not show the coloured buttons corresponding to the categories. Attached is a screenshot for reference. Does anyone know how to fix this? Many thanks, Thuy
Its very frustrating when you are adding multiple columns and having to use the slide bar to move to the end and then click the 3 dots and add another column. Seems there has to be an easier more productive way.