I am planning a project, so the exact start time is unknown yet.
I'd like to setup it so that I could change the start date once the project is approved, and have all the sequences/tasks updated.
Use Dependencies.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
First task would be "Project Start" or "Contract Award" or some such.
Craig
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…