Does Smart Sheet support multiple calendars similar to Projects where you can setup custom work days? If it doesn't how can I assign separate working days for different groups?
Only one calendar per sheet.
You can try separating tasks into multiple sheets by working days and then combining the results back together using Reports.
I did something similar with periodic meetings and international holidays.
Craig
Thanks again Craig, your help is appreciated.
Craig,
Are you saying you can combine multiple calendar sheets into 1 calendar sheet to be displayed?
Brian
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…