I am trying to interleave two project plans by linking activities across two sheets. The integrated workflow should be Task 1 -- Task 2 -- Task 3. Task 1 must complete before Task 2 begins. Task 2 must complete before Task 3 begins. Tasks 1 and 3 appear on Sheet A. Task 2 appears on Sheet B. I have created links for Task 1 on Sheet B, and the associated row is listed as a predecessor for Task 2. But when I create links to Task 2 on Sheet A, I cannot link the start date, and the activities do not cascade properly. When I try to create the link, the following error message appears: "You cannot create a link in this cell because its value is determined by a project dependency."