Hi there,
I'm building a schedule in Gantt View by back calculating from an end date. The issue I have (refer attached screenshot) is that I require the finish of the task at row 353 to be the earlier of the start of row 355 or 2 x weeks prior to the start of row 32. When I put in what I understand these predecessor formulas to be, the completion of task 353 is driven only by 2 x weeks prior to the start of task 32, but obviously it should be driven by the start of task 355 (as this is the earlier of the two dates).
Does anyone know what I am doing wrong here / how to fix it?
Thanks,
Paul