"Lag field"
CSCannon
✭
Unable to find the "Lag Field" Mentioned in this help screen:
Comments
-
CECannon,
When you click on a cell in the Predecessors column, there is a small edit icon (like an orange pen on my browser). Click that.
It will open up the Edit Predecessors dialog box.
Hope this helps.
Craig
-
You can also just type +/- # of days after the predecessor value. Like this:
5 + 7 (will automatically change to "5FS + 7d")
Predecessor is row 5 with 7 days of lag.
-
Per John's comment, duration and lags can take other time lengths.
http://help.smartsheet.com/customer/portal/articles/765737#Duration
Craig
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives