Is there a way to track duration by hours in a project plan (sheet)?
I know you can track by days, but what about hours? (
--Attached screenshot.
Hi,
You can input hours in the Duration cell, like 1h, 2h and so on.
Is this what you meant?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Yes! Where do I find that setting?
... not sure it is a setting, just type "1h" instead of "1" ...
Here's some more info on how it works.
https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#Duration
Duration
Duration represents the amount of time a task is expected to take. Click on the Duration cell of a sub-task and type in the length of time. You can use a few different formats:
Parent (summary) rows will always reflect duration in partial working days.
Andrée
Typing it in is easy - however - I am guessing that SS does not take any of that into account when adjusting task dates, correct?
Typing in 20h is easy, but how to do that a summary task also counts duration in hours? Even if I put all subtasks in hours, the summary task still sums everything to days and duration summary task cannot be edited..
I also had this issue @Sander K which isn't ideal but I believe there's a workaround to this through using formulas to convert and calculate it into the desired format.
I would love to say I was a Smartsheet formula whizz, but sadly I'm not. @Paul Newcome has created a thread, which contains a number of great solutions for calculating time. You can find this thread here: https://community.smartsheet.com/discussion/68947/formulas-for-calculating-time/p1.
It would be really good to know if/when such a solution is going to be released anytime soon? For me, along the lines of a time derived column, or a format/function that recognises and can calculate (and total/sum up) time easily - without the need for such complex and mammoth formulas.
It is something that would massively enhance Smartsheet at my organisation and would generate a larger user base, due to the increased number of use cases and workflows this would allow. I know that my organisation can't be the only other company who have been asking for this. By the look of the community pages, this is something that has been requested for a long time. @Smartsheet Admin Service Account @Smartsheet Administrator
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…