Duration vs Effort
Jeff Smith
âś
What I want to know is how to set up a project plan so that a resource is assigned for 2 weeks but is only having to do 40 hours of work over those 2 weeks. Is that the % Allocation?
Tags:
Comments
-
Yes the % allocation would be used for this. If they work 40 hour weeks and they are spending half their time on a task for two weeks, the allocation would be 50%.
Â
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 379 Global Discussions
- 210 Industry Talk
- 441 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 300 Events
- 33 Webinars
- 7.3K Forum Archives