Hi,
I have multiple projects to be managed under a program. I have a task1 under Project A which has dependency on task2 of Project B. How can I mark dependencies between two project tasks?
thanks,
Pragati
Hello,
Thanks for your post! It sounds like you haveĀ multiple Project Sheets, and some of these projects have tasks that are dependent upon tasks in other projects. Smartsheet doesn't currently support cross-sheet dependencies, but there are some workarounds that others have used. You can also submit a Product Enhancement Request with the quick link to the right.
To workaround this limitation, one option is to insert a row in the sheet which dependent sheet, then use cell links to populate the row with the task information from the sheet which contains the predecessor. Once this row is inserted and cell linked, you can then link tasks to this new row with predecessors.
Depending on the size of your projects, you may also be able to consolidate your Projects into a single Project Sheet with each project separated by a level of Hierarchy. I've included some related links below:
I hope this helps!
Isaac J
Smartsheet Support
Hi there! Our Account Manager today informed us that users would need to be paid members to receive and complete Update Requests going forward. I can't imagine that Form users would need to be members, but I don't know how that differs from Update Requests, since neither requires access to the underlying sheet. Is itā¦
This discussion was created from comments split from: Generate documents from row data.
Error occurs when opening Vault Apps in Smartsheet WorkApps. The app fails to load and displays an error message despite logging out and back in. Issue has been ongoing since last Monday