Hi!
I have 7 columns that have check boxes. When all 7 columns in one row are all checked, I would like a column that will auto populate a "completed" date. Is this even possible or am I insane? haha! Thank you!
This is not currently possible without a third-party solution like Zapier. There is no date-stamp option in Smartsheet although it is a HIGHLY requested item. I recommend that you submit a product enhancement request to add your vote to their list.
There is a possibility of adding a Modification date system column to your sheet, but anytime something changes on the row the modification date would change too.
Hi,
It's possible, but you would need to use a third-party tool like Zapier or similar.
Would that work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…
I have a workspace that I created with two subfolders. A user needs to have access to only one of them but when I have that folder selected, I can only share the entire workspace with them. Is there a secret way that I can share the parent folder and ensure that any new files created will be shared with the same people? I…
I have a Pro plan but I cannot create ANY reports. The system does not allow me to choose a folder, and consequently a sheet to create a row report and suggests an upgrade to Business or Enterprise. I'm quite new to Smartsheet and feel a bit disappointed with this limitation, or maybe I'm just doing something wrong. Alberto