I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?
Hello Zdiddy,
Thanks for your post! Assuming you're using the default Finish-to-Start dependencies, the dependent task's Start Date will always depend on the latest of the preceding task's End Dates. If you're using a different predecessor type or a combination of different predecessor types, then the important thing to know is that the Start (or Finish) of the dependent task will always depend on the latest of the preceding task's linked Start or Finish date. I've included a screenshot below.
I hope this helps!
Isaac J
Smartsheet Support
Hi All, Need you support for the the issue. I was in the process of making an approval workflow for petty cash request, the problem was when i want to combine 2 different confirmation workflow by Requester to be appear in same column (Confirm), but mention notification like in the screenshot attached. The workflow consist…
A report is not available to be a data source for a Metric Widget. I have a report that shows the one figure I want to be displayed on a dashboard. I cannot convert the report to a sheet and cannot seem to get the report number on my report to the Metric Widget… Can this functionality be added to use a report for a data…
I have a Smartsheet automation setup to reminder the planning to complete their sections. It is setup to remind weekly until completed box is checked. They received 2 reminders and then the reminders stopped. Any idea what could be wrong? I can't tell that anything has changed in the sheet. Thanks Freda