I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?
Hello Zdiddy,
Thanks for your post! Assuming you're using the default Finish-to-Start dependencies, the dependent task's Start Date will always depend on the latest of the preceding task's End Dates. If you're using a different predecessor type or a combination of different predecessor types, then the important thing to know is that the Start (or Finish) of the dependent task will always depend on the latest of the preceding task's linked Start or Finish date. I've included a screenshot below.
I hope this helps!
Isaac J
Smartsheet Support
It tells me this below and my QR links stopped working and there is no customer support even though i'm paying for this. formName: ajax formAction: fa_getLicensing serverStatus: false serverStatusText: CriticalException errorCode: 48
I am trying to sort dates within a Row Report and I keep getting results that are not in order. The Column type is a dropdown, and from what i have researched I understand the sort is dictated by the order of the dropdown. The dropdown is already in order by date in my source sheet. I have even created a separate column…
Hello, I am experiencing an issue with automations in Smartsheet. Some workflows continue to run normally, but others stop working intermittently even though they were previously functioning as expected. The issue does not appear to affect all automations, only certain ones. An important detail is that when the affected…