Double dependencies

Zdiddy
✭✭
I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?
Comments
-
Hello Zdiddy,
Thanks for your post! Assuming you're using the default Finish-to-Start dependencies, the dependent task's Start Date will always depend on the latest of the preceding task's End Dates. If you're using a different predecessor type or a combination of different predecessor types, then the important thing to know is that the Start (or Finish) of the dependent task will always depend on the latest of the preceding task's linked Start or Finish date. I've included a screenshot below.
I hope this helps!
Isaac J
Smartsheet Support
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.7K Get Help
- 472 Global Discussions
- 200 Use Cases
- 514 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 82 Community Job Board
- 520 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 307 Events
- 35 Webinars
- 7.3K Forum Archives