I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?
Hello Zdiddy,
Thanks for your post! Assuming you're using the default Finish-to-Start dependencies, the dependent task's Start Date will always depend on the latest of the preceding task's End Dates. If you're using a different predecessor type or a combination of different predecessor types, then the important thing to know is that the Start (or Finish) of the dependent task will always depend on the latest of the preceding task's linked Start or Finish date. I've included a screenshot below.
I hope this helps!
Isaac J
Smartsheet Support
This discussion was created from comments split from: Auto user provisioning.
This discussion was created from comments split from: Update request not showing fields for update.
Hi Team, How can I prevent a non admin end user from deleting a comment or comment thread in the dynamic view? Also, how can I notify the end user by email of the comment sent?