Double dependencies

Zdiddy
Zdiddy
edited 12/09/19 in Smartsheet Basics

I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?

Comments

  • Isaac Jose
    Isaac Jose Employee

    Hello Zdiddy,

    Thanks for your post! Assuming you're using the default Finish-to-Start dependencies, the dependent task's Start Date will always depend on the latest of the preceding task's End Dates. If you're using a different predecessor type or a combination of different predecessor types, then the important thing to know is that the Start (or Finish) of the dependent task will always depend on the latest of the preceding task's linked Start or Finish date. I've included a screenshot below. 

    I hope this helps!

    Isaac J

    Smartsheet Support

    Multiple Predecessors.PNG