Double dependencies
I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?
Comments
-
Hello Zdiddy,
Thanks for your post! Assuming you're using the default Finish-to-Start dependencies, the dependent task's Start Date will always depend on the latest of the preceding task's End Dates. If you're using a different predecessor type or a combination of different predecessor types, then the important thing to know is that the Start (or Finish) of the dependent task will always depend on the latest of the preceding task's linked Start or Finish date. I've included a screenshot below.
I hope this helps!
Isaac J
Smartsheet Support
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives