I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?
Hello Zdiddy,
Thanks for your post! Assuming you're using the default Finish-to-Start dependencies, the dependent task's Start Date will always depend on the latest of the preceding task's End Dates. If you're using a different predecessor type or a combination of different predecessor types, then the important thing to know is that the Start (or Finish) of the dependent task will always depend on the latest of the preceding task's linked Start or Finish date. I've included a screenshot below.
I hope this helps!
Isaac J
Smartsheet Support
I submitted a ticket, but thought I would ask here. I am having an issue with sheets that I own (our org is on a Business plan). For the last two years, we have been using the sheets without an issue - our admin and many Editors (all shown as Guest since they are outside of our organization) were able to edit the sheets…
Hello! I’ve noticed for a LONG time that when I change the name of a column in a source sheet, the corresponding column in reports breaks, which then causes dashboard widget charts (that rely on those reports) to fail. Is there a way to: Prevent this issue when renaming columns? Fix existing reports and dashboards without…
Dear All, my account was suspended for a long period in which my sheets were deleted. I renewed my account and asked technical support if my sheets could be recovered. I received this message below, but I do not seem to get a reply back afterwards and still do not have my sheets recovered. Thanks for…