Hello,
I have a question about resource view. At the moment, we just can see the projects under resources. But it’d be more helpful if we can see the tasks as well.
Is it possible?
And, can I see the whole projects FTE somewhere reported?
Regards,
Hello Leila,
Thanks for your post! There isn't currently a way to see the tasks that a resource is assigned to directly in the resource view. If you want to see specific tasks, you'll want to open the sheet itself and create a filter on the Contact List or Assigned To column to see tasks assigned to a the specific resource (https://help.smartsheet.com/articles/504659-using-filters-to-show-or-hide-sheet-data). If you want to see tasks assigned to specific people across multiple sheets, you can use a Smartsheet report (https://help.smartsheet.com/articles/522214-creating-reports).
By FTE, I presume that you're referring to Full Time Equivalent or the total workload capacity of the project overall, correct? There isn't currently a feature in Smartsheet that tracks the Full Time Equivalent for the project, however you can likely create a formula to track this. This will most likely be an AVGW (weighted average) function. For example, =AVGW([Allocation %]:[Allocation %], Duration:Duration) will return the average allocation percentage of all tasks in the project weighted by task duration, effectively giving you the overall FTE of the project (https://help.smartsheet.com/function/avgw)
If needed, you can submit a Product Enhancement Request with the quick link to the right.
I hope this helps!
Isaac J
Smartsheet Support
Hi and thanks. in the formula =AVGW([Allocation %]:[Allocation %], Duration:Duration) , instead of Allocation% I put effort and it does kind of make sense.
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…
I have a picture below for an example of this. I want to create a formula to get counts of items in "Column2", but if "Column4" states "change" I want the "Column2" count to not work and instead count what is it "Column3" in that given row. Column4 can also have several different things in it besides "good" that I want it…
I've done this a million times - create a report, separated by campus with a total $$. Then add it to a dashboard and make a graph. NOTHING is working right now when I try to do this. I get an error that the data cannot be charted. What the what? Help anyone? Is this a issue since they apparently changed something in the…