Hello SmartSheet community,
I would like to add bankholidays under a "depencies disabled" mode.
It this possible ?
I take it that with a "dependency enabled" mode, that's already feasible.
https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
Best
Hello,
At this time, dependancies must be enabled in order for non-working days or holidays to be excluded in the duration calculation.
As a workaround, you could create a formula using the NETWORKDAY function to calculate the number of days between two dates, adding 1 day to the result if the start date is a non-working day.
The NETWORKDAY function allows you to enter the dates you would like to exclude. More information on this function can be found here: https://help.smartsheet.com/function/networkday
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…