Is there a way to create dependencies between multiple sheets in a report.
can you provide more details about what you are trying to do?
Hi...I have the same question...
I typically manage or consult on multiple interdependent projects. I've tried managing dependencies across projects in different ways but none of them have been super successful.
For example, Project A - call it Telephone installation - has a dependency on Project B - call it, Network Infrastructure upgrade. They are being managed as two separate workstreams because of their content and resources, but at some point, work on project A will stop if Project B hasn't reached a certain point (usually a milestone).
I would like to (in the best case) show the dependency actually in the dependent project so that Project B is late, the remaining tasks of Project A slip. Alternate would be okay if I could just report on the dependencies and highlight pending problems.
Any suggestions would be appreciated...
Rob
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…
I am trying to send non-Smartsheets users information on forms. I know I can create a publicly accessible and editable link for the overall sheet/form, however, when I set up automated emails with links to the forms, the links to sheets/rows still require a login. Is there any way to get around it so that emails sent…
This discussion was created from comments split from: Generate documents from row data.