Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Hours don't translate over correctly to Gantt Chart
I'm entering 2 hrs in duration, but over in the gant chartt, it shows 2 days. advice on how to enter/view this corretly?
Comments
-
Carla,
Something looks odd.
Are Dependencies set?
Your "Start By" date shows 11/18 and your "Finish Date" shows 11/19 - which matches the Gantt chart.
Either Dependencies are not set or they are and the system is looking at the wrong or no Duration column.
Hope this helps
Craig
-
thanks Craig.
When I change the # of days (d), weeks (w), or minutes (m), the dates and Gantt Chart respond correctly, However, when I change it in hours (h), the dates and gantt chart respond as if it were days.
-
Carla, would you please share the sheet with me as an Admin so I can take a look?
travis.hannon@smartsheet.com
Thanks!
-
Thanks for sharing the sheet! In your project settings, you have your Length of Day set to 1 hour. When your day is 1 hour long, 2 hours will be two days.
Try changing your length of day to 8 hours (or however long your workday is).
-
I would not have guessed that one.
Craig
-
Awesome, Travis! Typo, should have been a 10...
Thanks so much!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives