I have an existing sheet that used from a template. It was imported from Project. There are currently no task names beside the bars in the Gantt chart. Is there a way to add the task name to show up to the right of the bars in the Gantt view?
Comments
-
Go to the Project Settings for the sheet, Timeline Display section, and select "Display Label for" dropdown for the column you want to see.
Β
If you want to see more than one, create a new column to concatenate the columns together.
Β
Craig
-
This worked for me. Thank you Craig.
-
Is it possible to add the name of the resource assigned to the task in the gantt view? And how about the % complete?
-
Hello,Β
Is there a way to add the task name to the left side of the bar instead of the right on the gantt?Β