Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Adding Task Name to Right Side of Bars
Comments
-
Go to the Project Settings for the sheet, Timeline Display section, and select "Display Label for" dropdown for the column you want to see.
If you want to see more than one, create a new column to concatenate the columns together.
Craig
-
This worked for me. Thank you Craig.
-
Is it possible to add the name of the resource assigned to the task in the gantt view? And how about the % complete?
-
Hello,
Is there a way to add the task name to the left side of the bar instead of the right on the gantt?
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives