Adding Task Name to Right Side of Bars
Comments
-
Go to the Project Settings for the sheet, Timeline Display section, and select "Display Label for" dropdown for the column you want to see.
If you want to see more than one, create a new column to concatenate the columns together.
Craig
-
This worked for me. Thank you Craig.
-
Is it possible to add the name of the resource assigned to the task in the gantt view? And how about the % complete?
-
Hello,
Is there a way to add the task name to the left side of the bar instead of the right on the gantt?
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives