Hi.
Ive just signed up for the free trial as I have a live project and I need something like Smartsheet.
I can't seen to work out how to create a new Primary Column.
What do I do ?
Thanks..
Hi Michael,
Welcome!
If you've created a sheet, there already is a Primary Column. It's probably the first one. (bold text)
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
More information about the Primary Column: https://help.smartsheet.com/articles/504645-primary-column
Hi Thanks
I might have the terminology wrong !
Im looking to add a new task, with sub tasks.
Happy to help!
I think you mean Parents / Children.
Information about Parents/Children: https://help.smartsheet.com/articles/504734-hierarchy-indenting-outdenting-rows
Hi and thanks
I think its a parent row I am trying to create, with children- I have 24 in total.
I can't see how to create a parent ! The indent doesnt show because I on an empty row. How do I add a parent ?
M..
If you insert a row above the 24 children/subtasks, right click on the first subtask row and select insert above and write something in the cell. Then select all subtasks and click on the Indent button in the toolbar (left of the Font selector).
The first row will become the Parent, and the subtasks will be Children.
Did it work?
Hi John
I have 24 tasks
I just want to know how to create a parent/ task name.
I can then enter the action/ child.
ID 1 - QFH project 05/22/19 11/22/19
ID 2 Scaffold 05/25/19 12/04/19
ID 3 Masonry 05/27/19 07/31/19 Sub-task; Start and finish 05/27/19 06/28/19 07/27/19 07/30/19
I need to end up with a sheet with 24 different ID's
Thanks.
Do you need help with this now or do you want to wait until our meeting?
Have a fantastic weekend!
Andrée
Did you get it working?
Hello Everybody, I am looking for a solution to move projects folders (control center) automatically after getting a milestone to another workspace or at least in another folder in a workspace. Is it possible? I don't have Bridge, but if I need Bridge to make this, I am also interested to understand how this would work.…
Hi! Our Fiscal Year begins in February. This means we are in fiscal year 2026, with the first quarter ending at the end of April. However, in my Smartsheet timeline, the year is off by a year. The timeline shows FY 2027 rather than FY 2026. Is there a way that I can change this?
Hi, I am a user for a paid plan, but for some reason, smart sheets stopped letting me edit. How do i fix this so that i can edit a dashboard? Thanks!