Hi.
I have a JIRA project that is comprised of tasks and sub-tasks.
The sub-tasks have remaining estimates that sum up at the task level.
For example, if I have 3 sub-tasks that have respectively 1, 2, and 3 days left are shown as 6 days remaining at the task level.
I sync it with Smartsheet, and I use the Remaining Time Estimate field from JIRA to translate into a Remaining Effort in Smartsheet.
The problem I see is that the Smartsheet Remaining Effort field is empty, although the same tasks in JIRA has 6d.
However, if I go and overwrite the parent Task Remaining Estimate field in JIRA to 6d THEN it will show up in Smartsheet.
Is this as designed or just me not getting it ?