For some tasks, the parent shows a percentage (e.g. 5%), others just a number (e.g. 0.9) (see attached). If I add new rows, the % shows, but I see no method to change the format of the non-% ones. Any ideas please.
Did you apply formatting to the entire column?
That can't be done as the column is locked by Project Settings due to activating dependency settings.
Damn, I rechecked and now the % format option is accessible. I clicked and problem solved.. Thanks for the pointer back to that.
I would check and make sure your dependencies are turned on as you indicated they were. I'm glad we got that problem solved!
Hello, I'm encountering an issue when attempting to copy certain Smartsheet sheets. When I try to "Save As New," the process consistently times out, indicated by a spinning cogwheel. On occasion, I also receive an error message stating that Smartsheet is unavailable. This problem is not affecting all of my sheets, only a…
Is it possible for dropdowns to filter by value? For example, my dropdown options are: Solar Battery, Winter Battery, PV Panels, PV Interconnections. If I type into a cell that uses this dropdown and enter “Battery,” none of the battery options appear. But if I type “PV,” then both “PV Panels” and “PV Interconnections”…
There are several instances when I make a new column in a sheet and want to add the description. The current set up is two different functions. Can the "Add Column Description" be added to this prompt box? I use several column formulas and automated columns that are also locked. In order to "Add Column Description", I have…