I may have a basic misunderstanding & need some clarification.
I have a task #3 (the Effective Date) of a contract. Further down the project I have another task....
#20 - Purchaser obtains an updated Survey & Title Commitment. Task #20 can begin on the Effective Date (task #3).
Further down the project I have another task #24 - Review Period that also begins the day after the Effective Date and runs for 45 days.
I set the the predesessors of task #20 - Finish-Start with task #3 & Finish-Finish with task #24.
In other words I want task #20 to begin on the Effective date and to finish the same time as task #24. Why does Smartsheet show the start & finish date both as the finish date of task #24, when it should start on the Effective Date? Actually I think Finish-Start will start it the day after the Effective Date.
Like I said, I think I have a little misunderstanding of the predesessors.
I sure would appreciate a clarification.....
Jerry