Hi,
I would like to present in report only rows which some of the cells has changed (Status, Due date, comments).
Is there a formula to track cell changes?
Thanks
Hi Michal,
Unfortunately, it's not possible at the moment, but it's a great idea!
Please submit an Enhancement Request when you have a moment.
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
As a workaround, you might use the Modified column and show the columns that you want to see in the report.
Would that work/help?
How can I do that?
Happy to help!
I'll write something up later today.
We could add the Modified as a criterion in the Report Builder and select what you want to include.
For example, we could select in the last seven days, and that would show everything that's modified over the last seven days. Then we'd add/remove so only the columns that you want to see would be included in the report and use the feature called Highlight Changes to highlight what has been changed in the last seven days.
Would that work?
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…