I would like to know how to calculate the% of progress that would correspond to a cut-off date.
In the MS Project it would correspond to the "Status Date".
Has anyone had any similar situation and been able to solve it?
Hi Gonzalo,
There currently isn't a way to automatically calculate the % Complete \based on date —the % Complete column needs to be manually filled in.
When you have a moment, submit a Product Enhancement Request to let our Product team know that you'd like to have this functionality in Smartsheet.
If needed, more information on % Complete can be found here: https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#Complete
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…