I have a Due Date column and Completion Date column, how do I set up a formula to show when the completion date is past the due date and highlights it?
Thanks
Hi
In order to do this I believe you need a "helper" column. This is a column set up on the sheet to provide some logic which will drive your conditional format. The helper column doesn't need to be visible.
I would set up a checkbox column called something like Is Overdue? with the following formula =IF([Completion Date]@row > [Date Due]@row, 1, 0)
Then in the conditional formatting screen you would use the Is Overdue column to define the formatting for the Completion Date column. See screen shot below.
Hope this helps
Debbie
Hi Amanda,
You'll need to use a so-called helper column with a formula that checks the dates and then use that for the conditional formatting rule.
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Would that work?
I hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
@Amanda Ollerenshaw
How did it go? Did you get it working?
✅Did this post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer. It will make it easier for others to find a solution or help to answer!
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…