Nested IF's Question

@Shannon Heizenrader

I am creating a post for you so that your question and whatever solution is found is public. That way anyone having a similar issue can find help and other people are also able to weigh in on a solution that may be a better fit.


YOUR QUESTION:

Hi, Paul,I am new to the community and using formulas. I apologize if this is not the right way to ask my questions. I am looking to add a formula that is similar to one you helped with here:

Paul NewcomeApr 19, 2019

Let's see if we can't simplify this a little bit and work in your extra criteria...Working Formula: =IF(OR([% Complete]1 = 1, [% Complete]1 > 0.6), "Green", IF(AND([% Complete]1 < 0.6, [% Complete]1 > 0), IF(NETWORKDAYS(TODAY(), [End Date]13) < 5, IF(NETWORKDAYS(TODAY(), [End Date]1) <= 3, "Red", "Yellow"), "Green"), "Gray")) Simplified Formula: =IF([% Complete]1 > 0.6, "Green", IF([% Complete]1 > 0, IF(NETWORKDAYS(TODAY(), [End Date]1) < 3, "Red", IF(NETWORKDAYS(TODAY(), [End Date]1) < 5, "Yellow")), IF([% Complete]1 = 0, "Gray"))) Simplified Formula + New Criteria: =IF([% Complete]1 > 0.6, IF(NETWORKDAYS(TODAY(), [End Date]1) < 2, "Red", "Green"), IF([% Complete]1 > 0, IF(NETWORKDAYS(TODAY(), [End Date]1) < 3, "Red", IF(NETWORKDAYS(TODAY(), [End Date]1) < 5, "Yellow")), IF([% Complete]1 = 0, "Gray")))


This is the logic from the original formula with my changes. I am trying to replace the colored balls in the original with text - Completed, Future start, Active and on track, Active with some concerns, Active with major concerns. My date columns are titled Start and Finish.-If Complete% is 100% = Green - Completed - If Complete% is upper 60% = Green - Active and on track - if Complete% is under 60% and Today is less 5 days before End date = Yellow - Active with some concerns - if Complete% is under 60% and Today is less 3 days before End date OR behind End date = Red - Active with major concerns- If Complete% is 0 = Gray - Future start- Even if complete% is upper 60%, Today is less 2 days before End date = Red - Active with some concerns

I modified your formula to this:=IF([% Complete]1 = 1, "Completed", IF([% Complete]1 > 0.6, IF(NETWORKDAYS(TODAY(), [Finish]1) < 2, "Active with major concerns", "Active and on track"), IF([% Complete]1 > 0, IF(NETWORKDAYS(Start(), [Finish]1) < 3, "Active with major concerns", IF(NETWORKDAYS(Start(), [Finish]1) < 5, "Active with some concerns"), "Active and on track"), IF([% Complete]1 = 0, "Future start"))))I am still getting an unparseable result. Can you help me figure out what I am missing?Thank you!Shannon


I will review your question and post my response in the comment section.

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!