Formula for Calculating Dates

Installation date, need to add 2 weeks prior to start follow up to upcoming information (This will be on the left of the Installation date column)
This discussion was created from comments split from: Calculate Future Date.
Best Answer
-
If I'm understanding your question correctly-- are you saying you need a formula that calculates 2 weeks before the install date?
=[Installation Date]@row-14
Should populate your install date - 14 days
Answers
-
I need formula to calculate a date to start checking on a column example
Installation date, need to add 2 weeks prior to start follow up to upcoming information (This will be on the left of the Installation date column)
-
If I'm understanding your question correctly-- are you saying you need a formula that calculates 2 weeks before the install date?
=[Installation Date]@row-14
Should populate your install date - 14 days
-
Yes thanks!
-