Formula for Calculating Dates

Installation date, need to add 2 weeks prior to start follow up to upcoming information (This will be on the left of the Installation date column)
This discussion was created from comments split from: Calculate Future Date.
Best Answer
-
If I'm understanding your question correctly-- are you saying you need a formula that calculates 2 weeks before the install date?
=[Installation Date]@row-14
Should populate your install date - 14 days
Answers
-
I need formula to calculate a date to start checking on a column example
Installation date, need to add 2 weeks prior to start follow up to upcoming information (This will be on the left of the Installation date column)
-
If I'm understanding your question correctly-- are you saying you need a formula that calculates 2 weeks before the install date?
=[Installation Date]@row-14
Should populate your install date - 14 days
-
Yes thanks!
-
Excellent! Please don't forget to mark the most appropriate response(s) as "helpful" so that others looking for a similar solution know that one can be found here.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66K Get Help
- 429 Global Discussions
- 149 Industry Talk
- 488 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 153 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!