automation - mark Main Task 100% complete and Status=Complete when all sub tasks are complete
Answers
-
@Cyndi You are going to want something like this...
=IF(COUNTIFS(CHILDREN(), "Complete") = COUNT(CHILDREN()), "Complete", IF(COUNTIFS(CHILDREN(), "Not Started") = COUNT(CHILDREN()), "Not Started", "In Process"))