how to realize a projectplan with planned start/end/effort/duration vs. actual start/end/effort/....
Hi all,
we are successfull planning projects with smartsheet.
Now we would like to compare planned start/end/effort/duration vs. actual start/end/effort/duration.
Any idea how to do that? Baseplans? How to visualice two gantt bars planned vs. actual ( vs. base x plan)
Thank you and best wishes, Joachim
Answers
-
To visualize both Gantt bars, you would need to first create the baseline project plan. Then you would make a copy of it for your actual project plan. You can reference both sheets in a report to show each deliverable's baseline and actual dates on the Gantt similar to
Deliverable 1 Baseline
Deliverable 1 Actual
Deliverable 2 Baseline
Deliverable 2 Actual
-
good idea, but seems not to be very usable
a report will not show the outlining structure parent - child
also I do not know how to sort the projects, phases, tasks and subtasks in the report to have them in the same order but actual and base lines are beside each other.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!