how to realize a projectplan with planned start/end/effort/duration vs. actual start/end/effort/....
Hi all,
we are successfull planning projects with smartsheet.
Now we would like to compare planned start/end/effort/duration vs. actual start/end/effort/duration.
Any idea how to do that? Baseplans? How to visualice two gantt bars planned vs. actual ( vs. base x plan)
Thank you and best wishes, Joachim
Answers
-
To visualize both Gantt bars, you would need to first create the baseline project plan. Then you would make a copy of it for your actual project plan. You can reference both sheets in a report to show each deliverable's baseline and actual dates on the Gantt similar to
Deliverable 1 Baseline
Deliverable 1 Actual
Deliverable 2 Baseline
Deliverable 2 Actual
thinkspi.com
0 -
good idea, but seems not to be very usable
a report will not show the outlining structure parent - child
also I do not know how to sort the projects, phases, tasks and subtasks in the report to have them in the same order but actual and base lines are beside each other.