I have tasks with dates that overlap can I set this up on a gantt chart?
How can I link tasks that overlap?
Answers
-
Hi @Kathryn Leaney,
I'm not sure this is currently possible —the only way I know of linking tasks is by using predecessors. However, I'm not sure this would work for your use case because when you create a predecessor relationship between two tasks, the dates auto-adjust to fulfill the predecessor relationship defined.
Could you elaborate on how you would like this to work?
If needed, more information on predecessors can be found in our help article: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 423 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 144 Just for fun
- 59 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!