Multiple IF/AND Formulas - Need Nesting Help
I am in need of some assistance with a formula.
Here is a snap shot of the sheet I am working with:
I am trying to create a formula for the Activity Health Status field that drives the RYG ball.
I want it to do the following:
Blue
Tasks that show status of “Complete”
Red
Tasks that show status of “In Progress” and finish date is within the next 2 days and % Complete is less than 50%
Tasks that show status of “In Progress” and finish date is in the past
Tasks that show status of “Not Started” and the start date is in the past
Tasks that show status of “Not Started” and the finish date is in the past
Yellow
Tasks that show status of “In Progress” and finish date is within the next 4 days and % Complete is less than 50%
Green
Tasks that show a status, start and finish date and % complete but do not meet the criteria above
Error
If there is an error (start/finish dates, % complete, or status fields are blank etc) – No color appears
I have tried myself to come up with an IF formula; however, my nesting skills are not that great so it always comes up as UNPARISHABLE. I have reviewed info on the IF, IFERROR, NETWORKDAYS, AND/OR etc but cannot figure it out.
This is something needed ASAP. Can you assist?
I have gotten this far with the formulas (I think these are correct individually); however, I do not know how to nest them together:
Blue
1. Tasks that show status of “Complete”
=IF([% Complete]@row=1, "Blue")
Red
2. Tasks that show status of “In Progress” and finish date is in the past
=IF(AND(Status@row = "In Progress", TODAY() > [Finish Date]@row), "Red", "")
3. Tasks that show status of “Not Started” and the start date is in the past
=IF(AND(Status@row = "Not Started", TODAY() > [Start Date]@row), "Red", "")
4. Tasks that show status of “Not Started” and the finish date is in the past
=IF(AND(Status@row = "Not Started", TODAY() > [Finish Date]@row), "Red", "")
5. Tasks that show status of “In Progress” and finish date is within the next 2 days and % Complete is less than 50%
=IF(AND([Status]@row ="In Progress", (NETWORKDAYS(TODAY(), [Finish Date]@row) <3), [% Complete]@row <50), "Red", "")
Yellow
6. Tasks that show status of “In Progress” and finish date is within the next 4 days and % Complete is less than 50%
=IF(AND([Status]@row ="In Progress", (NETWORKDAYS(TODAY(), [Finish Date]@row) <5), [% Complete]@row <50), "Yellow", "")
Green
Tasks that show a status, start and finish date and % complete but do not meet the criteria above
Put “Green” at the end of the formula?
Error/If Blanks
If there is an error (start/finish dates, % complete, or status fields are blank etc) – No color appears
Put IFERROR and “” at the end of the formula?
Any assistance would be greatly appreciated!
Answers
-
Try this one...
=IF(OR([Start Date]@row = "", [Finish Date]@row = "", [% Complete]@row = "", Status@row = ""), "", IF(Status@row = "Complete", "Blue", IF(OR([Finish Date]@row < TODAY(), AND([Start Date]@row < TODAY(), Status@row = "Not Started"), AND(NETWORKDAYS(TODAY(), [Finish Date]@row) <= 2, [% Complete]@row < .5)), "Red", IF(AND(NETWORKDAYS(TODAY(), [Finish Date]@row) <= 4, Status@row = "In Progress", [% Complete@row < .5), "Yellow", "Green"))))
-
I tried this but it still reads as UNPARISHABLE.
Someone else used the info I had above and came up with this that seems to work:
=IF(ISBLANK(Status@row), " ", IF(ISBLANK([Start Date]@row), " ", IF(ISBLANK([Finish Date]@row), " ", IF(ISBLANK([% Complete]@row), " ", IF([% Complete]@row = 1, "Blue", IF(AND(Status@row = "In Progress", TODAY() > [Finish Date]@row), "Red", IF(AND(Status@row = "Not Started", TODAY() > [Start Date]@row), "Red", IF(AND(Status@row = "Not Started", TODAY() > [Finish Date]@row), "Red", IF(AND(Status@row = "In Progress", (NETWORKDAYS(TODAY(), [Finish Date]@row) < 3), [% Complete]@row < 50), "Red", IF(AND(Status@row = "In Progress", (NETWORKDAYS(TODAY(), [Finish Date]@row) < 5), [% Complete]@row < 50), "Yellow", "Green"))))))))))
It seems to work; however, it appears yours is much more condensed. Is there a way to condense the one I have listed above?
-
I think I got yours to work! It was just missing a bracket ] at the end of the formula. You had:
[% Complete@row < .5), "Yellow", "Green"))))
I added the bracket:
[% Complete]@row < .5), "Yellow", "Green"))))
And now it works!
=IF(OR([Start Date]@row = "", [Finish Date]@row = "", [% Complete]@row = "", Status@row = ""), "", IF(Status@row = "Complete", "Blue", IF(OR([Finish Date]@row < TODAY(), AND([Start Date]@row < TODAY(), Status@row = "Not Started"), AND(NETWORKDAYS(TODAY(), [Finish Date]@row) <= 2, [% Complete]@row < .5)), "Red", IF(AND(NETWORKDAYS(TODAY(), [Finish Date]@row) <= 4, Status@row = "In Progress", [% Complete]@row < .5), "Yellow", "Green"))))
Couldn't thank you enough!
-
@Tiffanie Teater Sorry about that. Those brackets always get me. Ugh. I'm glad you were able to catch that!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 145 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!