In regards to the resource allocation, is there a way to assign multiple resources per task with different allocations?
Microsoft Project allows this by typing " ResourceA (20%), ResourceB (40%)" in the resource name section.
It seems like in the Smartsheet, even though you can assign multiple resources to a task, you can only assign one allocation %.
Any help is appreciated!