What formula would I use to calculate 120 prior to a date listed in my sheet?
This is the formula I tried and it is #UNPARSABLE.
Best Answer
-
You need to use WORKDAY function here.
WORKDAY([Renewal Date]3, -120)
Answers
-
You need to use WORKDAY function here.
WORKDAY([Renewal Date]3, -120)