% Complete Formula based on Start/Finish Dates

Options
2»

Answers

  • Genevieve P.
    Genevieve P. Employee Admin
    Options

    Not dumb at all! It's a great question, @Jeff Casto.

    The reason for this will be because you're using Dependencies in this sheet, which then limits what columns you can use for formulas (see: Areas where formula use is restricted)

    Specifically, the % column already has a formula applied relating to the Hierarchy in your sheet. It creates a "Parent Rollup" percent complete, weighting the Parent row % by the duration and manually applied % of the Child Rows, see: Parent Rollup Functionality

    Notice how both of my Parents have 2 tasks, one at 100% and one at 0%. The Parent Rollup functionality in the % column has a formula that determines the Parent's % based on the duration of the children... so my first summary row is 50% complete (1 task of 1 day at 100%, 1 task of 1 day at 0%), whereas the other summary row is only 1% complete, since the second child has 143 days duration and is at 0%.

    I hope that helps!

    Genevieve

  • Jeff Casto
    Jeff Casto ✭✭✭
    Options

    Wow, @Genevieve P. this is great information. Thank you again so much.

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!