Report building
Can I build a report that shows all items due in last 7 days and next 7 days, AND all items due if they are late (even if more than 7 days due?)
I can figure out how to condition my report on both those items,
Answers
-
Try setting up your report like so...
-
Thanks! this is helpful. But is there is a way to show
a) All Tasks in the last 7 days and next 7 days, regardless if they are done or not
AND
b) all tasks that are in the past (beyond 7 days) and not yet done
-
Ah. Ok. I understand now. It may be easier to use a helper checkbox column on the sheet that contains a formula to automatically check the boxes on applicable rows and then build your report off of that checkbox column.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!