I want task due dates to auto populate based on one date that I enter as the event date. For example, I will set an event date and certain tasks will be due 2 weeks prior to event date. When I create individual event sheets, I want to enter that event date and then due dates will auto populate for each event based on that date.
Comments
-
=WORKDAY([Start Date]1, -14)
-
Dion,
If you project settings have Dependencies enabled, use Predecessors.
Sounds like you want to work backwards from the end date, so use something like this:
https://www.smartsheet.com/blog/support-tip-work-back-schedule
Craig
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives