Duration and finish dates
Hello
Is it possible to create a Formula or another way to do the following
example:
Industry Injection mold making
I have allotted 5 days for a task. ie starting on Monday- finish Friday
once finished they move to the next operation. start on the following Monday
I have a check box to machine the parts. in progress another for completed
the operator finishes one day early . I would like to click the finish check box and have the finish date moved back a day. thus moving the next operation to start on Friday.
is it possible to have the predecessor also cleared
I would then like the next operation check box to move the start date up.
thanks for any help
Gord
Answers
-
Gordon, the End Date and Predecessor columns in a Smartsheet project plan cannot contain formulas, so there is no way to do what you want currently and have it reflected in the Gantt.
A suggestion is that once you mark something as complete, you can highlight the row with conditional formatting as a reminder to make the changes manually.
Cheers,
Ramzi
Ramzi Khuri - Principal Consultant @ Cedar Tree Consulting (www.cedartreeconsulting.com)
Feel free to email me: ramzi@cedartreeconsulting.com
💡 If this post helped you out, please help the Community by marking it as the accepted answer/helpful.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 63 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!