Calculating the difference between Estimated Duration (Part of the Project Settings) and Actual.

Hi ,

Estimated Duration is part of the Project settings and drives the start and finish date.

I want to calculate the difference between estimate and actual . We want to track in hours. i.e .25h = 15 min.

The only way I can get the calculation to work is .25 days but that is really 2 hours, not 15 min.

Estimated Duration - Actual Duration= Duration Difference

How do I calculate the difference with keeping the Estimated and Actual in Hours?

image.png


Best Answer

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!