Tasks cannot be linked with predecessor if date is fixed in past
Tasks cannot be linked with predecessor if date is fixed in past, MS project will allow start or finish no earlier than date with a predecessor allocated to drive the date accordingly.
Are there plans to add functionality for task dates to be start or finish no earlier or later, with a predecessor allocated driving the date out where applicable?
Thanks
Answers
-
Hi @Dan Harris
Great question! From what it sounds like, you're looking for a feature that would be similar to the Constraint function within Microsoft.
Please let our Product team know about your interest in this feature by Submitting a Product Enhancement Request. Your request will go directly to our Product team to review for possible future production.
To keep up to date with our newest releases, check out our Release Notes here: https://www.smartsheet.com/content-center/product-news/release-notes/all
Thanks!
ToriLynn
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.3K Get Help
- 364 Global Discussions
- 199 Industry Talk
- 428 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 445 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!