Project Template
Hello!
I am utilizing the Project Template to create a Comm Flow plan. I am getting bit hung up on the predecessors and dependencies. I need the calendar to highlight 3 things. Is it possible for the sheet to highlight 3 separate dates on the calendar without being a bar? AND is there any way to make those 3 separate dates different colors?
THANK YOU!
Tiffany
Best Answer
-
Hi @Tiffany Holohan !
Usually when using Gantt, you can highlight a significant event by creating a Milestone, this will make the special date a diamond on the chart. Unfortunately, at this time, you can't change the colors of the milestones.
Erin Greunke
Sr. Program Manager, Smartsheet Beta Programming
Answers
-
Hi @Tiffany Holohan !
Usually when using Gantt, you can highlight a significant event by creating a Milestone, this will make the special date a diamond on the chart. Unfortunately, at this time, you can't change the colors of the milestones.
Erin Greunke
Sr. Program Manager, Smartsheet Beta Programming -
Thank you so much for that information! I like the diamond. Another question: can there be multiple Bars/Diamonds in the Gnatt template on a single row?
I am also having trouble deciding on the dependencies.
THANK YOU SO MUCH!
Tiffany
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.3K Get Help
- 390 Global Discussions
- 212 Industry Talk
- 446 Announcements
- 4.6K Ideas & Feature Requests
- 141 Brandfolder
- 132 Just for fun
- 131 Community Job Board
- 453 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 292 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!