We have a combination of production activities that go round the clock and people related activities that don't use weekends.
IN Microsoft Project, I am either to get around this issue by either setting a 7 day a week calendar OR using elapsed times in durations and as values for lags in Predecessor.
In smart sheets, I am able to use a 7 day a week calendar (which works for me) but does not work for the Rolled up calendar I am trying to link to. THey use a 5 day calendar and this throw all the values off.
I am able use elapsed time e5d in duration but I am not able to use the same value in predeccesor 5FS+e5d. Smart sheets seems unable to use elapsed time in the predecessor column.
ANy suggestions?