Networkdays Help
Hi. I am trying to calculate the number of workdays between 2 dates. I have a table on a different sheet showing my complete project calendar differentiating between Workdays, Non-Workdays and Holidays (see below):
Any ideas on how I should structure the formula so that the calculation between the two dates exclude the non-working and holiday dates obtained from the above table.
Thanks
Answers
-
Hello @Chris Dijkstra ,
If you were to use a Project Sheet, you could define in the Project settings what days are working days, as well as specific holidays. The Project Sheet's have a Duration Column that automatically calculates the Working days between two dates. Please see my example below:
If you wanted to do this out with a Project Sheet, in your Sheet where you define Non Working Days, I would remove all the "Workdays", and just keep this column to show Non-Working Days/Holidays. Please see my below example.
The Formula I used was: =NETWORKDAYS(Start@row, End@row, {NonWorkDays/Holidays Range 1})
Here's my Sheet with the date range:
Here's my Sheet with the list of Non-Work days, and Holidays:
Let me know if you have any questions!
Regards
Sean
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 145 Just for fun
- 62 Community Job Board
- 464 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!