Hello,
Question regarding the display of section headings in Gantt charts:
I would like for the section heading to only show the times when that section is active, rather than the whole window between the first day active and the last day active.
An example- one of the Gantt section headings I am using is "Painting". Two of the sub-sections are "Bathroom painting" and "Bedroom painting". "Bathroom painting" is taking place between Jan 5 and Jan 10, and "Bedroom painting" is taking place between Jan 25 and Jan 30. So, the whole painting section is taking 10 days.
However, when I put that information in, the "Painting" Section heading looks like it is taking place the whole time between Jan 5 and Jan 30, so a total of 25 days. I understand why it is doing this, but I would prefer if it only showed the time it was active, so it would be clear how long the whole Painting category is actually taking.
Is there an easy way to do this? I would prefer not to break out "Bathroom painting" and "Bedroom painting" in to their own separate sections, since I would have to do that for all other categories as well.
Thanks in advance for your help.