Has the ability to adjust a resources work schedule been added?
Hi Shawn,
There currently isn't a way to set working time per resource in Smartsheet but I've added your vote for this to our enhancment request list for further consideration.
Thanks for your input!
Shaine:
Please add my vote for this because we desperately need to work with our resources schedule and right now it seems to be an endless task...
Mariemma
OMG it's 2019, this has been a feature with MS Project 2001 when I learned it back then.. I don't know what beyond "a nice picture" Smartsheet can be if you can't individually schedule resources (as in contract employes, not static scheduled factory workers)..