Using % Planned (completed in the automated Smartsheet Project Setting) and % completed
Hi All
Apologies if this is a little simplistic but.....I need to show % planned (ie planned time for completion), which is calculated by the project setting. I also need to show % Completed which will be a roll up of manually inputted %'s as we complete tasks (against all of the rows the project setting populates). This is to to show completion vs time planned.
Does anyone have a formula for calculating % Complete (which is effectively a duplicate of the project settings formula but with the tasks % completion being manually inputted)?
Thanks so much!!
R
Answers
-
Hi Rowan,
If you have rows with Parent/Children relationships, you could simply put the following formula in the % Completed column of the Parent Row:
=AVG(CHILDREN())
This would calculate the value based on the percentages manually inputted in the underlying/children tasks.
Help Article Resources
Categories
Check out the Formula Handbook template!