Using % Planned (completed in the automated Smartsheet Project Setting) and % completed
Hi All
Apologies if this is a little simplistic but.....I need to show % planned (ie planned time for completion), which is calculated by the project setting. I also need to show % Completed which will be a roll up of manually inputted %'s as we complete tasks (against all of the rows the project setting populates). This is to to show completion vs time planned.
Does anyone have a formula for calculating % Complete (which is effectively a duplicate of the project settings formula but with the tasks % completion being manually inputted)?
Thanks so much!!
R
Answers
-
Hi Rowan,
If you have rows with Parent/Children relationships, you could simply put the following formula in the % Completed column of the Parent Row:
=AVG(CHILDREN())
This would calculate the value based on the percentages manually inputted in the underlying/children tasks.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!