Can the % complete for a subtask be updated with a formula?
Hello, I am trying to figure out if it is possible to update subtask % complete to automatically update via a formula or input from another field.
Thanks in advance!
Answers
-
Is the % Complete column being used in the dependency settings?
-
Yes it is.
-
Then you would not be able to use a formula. Formulas cannot be used in columns that are referenced in the dependency settings.