Displaying Actual Start/Actual Finish
Hi I have a chain of dependent tasks that all start on the same day, but because they are dependent, they waterfall out in the gantt. Is there a way to display the actual task start and finish dates in a column?
Answers
-
If I'm understanding you correctly, you have a number of tasks set up like this, each dependent on the task above:
But instead, you want them to still be dependent, but start on the same day (instead of when the other task ends). If so, you can indicate that you want the dependency to be a Start - to - Start type of dependency by adding SS after the Predecessor number, like so: 1SS
Here's an article that you may find useful as you set up your project: Change the Attributes for a Predecessor Relationship
Cheers!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.6K Get Help
- 403 Global Discussions
- 215 Industry Talk
- 455 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 56 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!