auto populate a date field
I would like to auto populate a "due date" field based off another date field on my sheet. I have an event date that reads from a request form and I want to have a task due date auto fill based off the event date.
Thanks!
Bob
Best Answers
-
Try
=[Date of Session]@row - 7
-
Perfect! Thanks Paul.
Answers
-
Hi @Bob Kernan
Can you describe your process in more detail and maybe share the sheet(s)/copies of the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@workbold.com)
I hope that helps!
Be safe and have a fantastic weekend!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
OK, the screen shot below has the two columns I need to work with. The "Date of Session" field is going to auto-populate from a form that gets filled out. That part I am good with. What I want to happen is When the "Date of Session" populates, the "Deck Due Date" will autofill with a date that is 7 days prior to the "Date of Session".
-
Try
=[Date of Session]@row - 7
-
Perfect! Thanks Paul.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.1K Get Help
- 430 Global Discussions
- 149 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!