Average duration for a specific type
I am trying to calculate the average time (based on #2) per request type (i.e multiple request types and trying to get the average per type in my Request Metrics form)
Columns:
- Request Type
- Actual Days to Completion (this is calculated via formula of date ending - date initiated)
I am not really sure where to start with this formula but any advice would be greatly appreciated.
Best,
Jodi
Answers
-
You are going to want to use something along the lines of...
=AVG(COLLECT({range to average}, {request type range}, @cell = "Request Type"))
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!