Hello,
I am trying to do resource capacity planning, but at the project level.
Here is my setup:
- I have one project per sheet
- Each projects are quite small, they have around 15-20 tasks and subtasks
- I use dependencies and resource management
- Here is an example of a project:
I want to assign the whole project to a single person, at let's say, 30% of his time.
I cannot set the "% Allocation" field for the first row as it has children.
What are my options for assigning the whole project to a single person, set an Allocation percentage, have that percentage taken into account in Resource Management ?
Thanks for your help,
Charles