Start time before 8AM
I am using duration column in increments of e10m, e30m, etc. But I cannot get my start time before 8AM. I want my working hours to be 5AM - 10PM. How do I do this without making it a 24 hour clock?
Answers
-
If you go into your project settings you can adjust your length of day to be a certain number of hours. Is that what you mean?
Regards
J Tech
If my response has helped you in any way or provided a solution to your problem, please consider supporting the community by marking it as Insightful, Vote Up, or Awesome. Additionally, you can mark it as the accepted answer, which will make it easier for others to find a solution or get help with a similar issue in the future. Your support is greatly appreciated!
-
If I adjust the length of day the time still starts at 8AM, the end time becomes longer. I need to adjust the working hours so my start time can be 5AM
-
I had the same problem. I like to show tasks that are supposed to start the next day starts 9:00 AM in the plan because the company uses CST and employees begin to work at 9:00 AM.
Lacking this feature makes SMARTSHEET useless as a minute-by-minute planning tool.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!