Start time before 8AM

I am using duration column in increments of e10m, e30m, etc. But I cannot get my start time before 8AM. I want my working hours to be 5AM - 10PM. How do I do this without making it a 24 hour clock?

Answers

  • J Tech
    J Tech ✭✭✭✭✭

    If you go into your project settings you can adjust your length of day to be a certain number of hours. Is that what you mean?

    Regards

    J Tech

    If my response has helped you in any way or provided a solution to your problem, please consider supporting the community by marking it as Insightful, Vote Up, or Awesome. Additionally, you can mark it as the accepted answer, which will make it easier for others to find a solution or get help with a similar issue in the future. Your support is greatly appreciated!
  • Gina Prego
    Gina Prego ✭✭✭

    If I adjust the length of day the time still starts at 8AM, the end time becomes longer. I need to adjust the working hours so my start time can be 5AM

  • I had the same problem. I like to show tasks that are supposed to start the next day starts 9:00 AM in the plan because the company uses CST and employees begin to work at 9:00 AM.

    Lacking this feature makes SMARTSHEET useless as a minute-by-minute planning tool.